Camel group resource recycling Xiangyang co., ltd. annual output of 50000 tons of power lithium battery recycling and echelon utilization project technical transformation environmental impact assessment a publicity

Release time:2023-02-17


According to the relevant provisions of the "the People's Republic of China Environmental Impact Assessment Law", the "Regulations on Environmental Protection Management of Construction Projects" and the "Measures for Public Participation in Environmental Impact Assessment" and the requirements of the Ministry of Ecological Environment Order (Ministry Order No. 4), the relevant information on the environmental impact assessment of the technical transformation of the 50000-ton power lithium battery recovery and cascade utilization project of Camel Group Resource Recycling Xiangyang Co., Ltd. is now publicized as follows:

1. Project Overview

Project name: annual output of 50000 tons of power lithium battery recycling and echelon utilization project technical transformation

Construction address: Jinyang Avenue, Gucheng Economic Development Zone (Sujiapan, Baojia Bay)

Project nature: technical improvement and others

Overview of the construction project: new lithium battery recycling production technology and equipment are adopted to replace the original plan, and the layout and pollution control facilities of the factory are adjusted according to the requirements of the new technology and equipment. The completed power lithium battery recycling line will be used as a test line. After technological transformation, the total production capacity of the whole plant will remain unchanged at 15000 tons of waste power batteries per year for cascade utilization and 35000 tons of waste power batteries per year for recycling.

Name and contact information of 2. construction unit

Name of Employer: Camel Group Resource Recycling Xiangyang Co., Ltd.

Unit Address: Jinyang Avenue, Gucheng Economic Development Zone (Su Jiaban, Bao Jiawan)

Contact person and telephone number: Hu Gong 13972054360

The name and contact information of the environmental impact assessment institution undertaking the environmental impact assessment work of the 3..

Unit name: hubei wanrui environmental protection co., LTD

Address: No. 66 Pang De Road, High-tech Zone, Xiangyang City

Contact: Bian Gong

Tel: 0710-3105998

Web link to 4. public comment form

Web Links to Public Opinion Form: https://pan.baidu.com/s/1JC46HUFErf7vRDoh93PHRw?tdsourcetag=s_pcqq_aiomsg&qq-pf-to=pcqq. C2C

Main matters 5. soliciting public opinions

In order to listen to the opinions and suggestions of all walks of life on the environmental protection work of the project, the construction project is publicized and the public opinions and suggestions are solicited. The main contents are as follows:

(1) The public's information sources, site selection views and attitudes towards the project;

(2) The public's understanding of whether the project construction promotes economic and social development;

(3) Public awareness of the environmental impact of the project on individual interests;

(4) Environmental countermeasures that the public considers necessary for the environmental problem of greatest concern;

(5) Public opinions, suggestions and specific requirements on the environmental protection measures of the project;

(6) The public's attitude towards the environmental impact of the project construction.

Public Participation in 6. Environmental Impact Assessment

Direct contact with the construction unit or EIA unit undertaking the EIA work by written opinion, email, telephone, etc.

Publicity time: within 10 working days from the date of publicity.

7. Description

1. Within ten working days from the date of publicity, the construction unit or the entrusted environmental impact assessment unit shall provide the public with relevant information inquiry and inspection services;

2. The public's opinions or suggestions on the construction project may be submitted to the construction unit or the environmental assessment unit within ten working days from the date of publicity.